
Project
Development of International Mineral Agreement for Exploration of Copper & Gold and associated minerals at Reko Diq, District Chagai, Balochistan

Project Details
Project Description
This large-scale integrated mining and power project was undertaken in collaboration with Australasian Continental Energy Pvt Ltd (AACE), Australia. The project aimed to develop opencast mining operations with a capacity of 18 million tons per annum (MTPA) of coal to fuel a 3000 MW power generation facility. It was designed to ensure long-term energy security by utilizing Pakistan’s vast Thar coal reserves.


Key features of the project were based on the following three stages:
- Mining Bankable Feasibility Study (BFS)
- Coal reserves to JORC standard (confirmation)
- Extraction process
- Mine Design
- Plant design
- Equipment and infrastructure requirements
- Environmental issues
- Financial viability
- Hydrogeology
- Social Impact Studies
- Alternative processing methods
- Mining operations were planned for uninterrupted coal supply for power generation.
- Power Generation
Want to connect with us?
About Us
DES Private Limited has been providing expert consultancy and technical services in cement, mineral exploration, and industrial sectors for over 26 years.
Phone:
+92 42 35455755
Email:
Address:
31-E, Block J III, Johar Town, Lahore, Pakistan
Monday – Friday: 9:00 AM to 5:00 PM